Green light to the realization of an area for the industrial logistics in the port of Piombino

The participations about 200 thousand extend on a surface square metres

Committee Technical Amministrativo of Provveditorato Interregional to Public works Tuscany-Marche-Umbria, that it has advisory functions for works whose amount is inferior to 50 million euros, has given own opinion favorable to the project for the execution of work of infrastructuring for the realization of an area for the industrial logistics in the port of Piombino.

The green light allows with the Authority of Harbour System of the Tyrrhenian Sea Northern to proceed with the predisposition of the executive project and the next ban of contest. The AdSP has specified that with these participations it will be possible to give substance to the takeover of Baker Hughes (BHGE) - New Pignone in the port of Piombino.

The participations extend on a surface about 200 thousand square metres and consist in the complete infrastructuring of the area and in the completion of the practicability of access to the areas of the Dock North.

The work is finalized to the realization of a equipped area to assign to the industrial logistics. Between the previewed works, the completion of the practicability of access to the Dock North in prosecuzione of the new road of income to the port (Extract SS 398 of the interchange Gagno- Terre Rosse); it rests in work of the distribution networks of the internal services to the area and of the nets of necessary services for the development of the industrial activities; the preparation of the antifire net, the realization of the structures of foundation of the main manufactured products to realize in the area and accommodation to green of the land stripe that coasts the participation area.

The project is divided in two phases, in the earlier stage work that comprise all the works, services and systems will be realized that interest the western portion of the area of recovery to the sea and the first septum of the waterproof bathtub for a surface of 150 thousand square metres while in the second one square metres will be realized the same work for the remaining portion of 48 thousand.

Altogether the estimated time in order to realize the two phases is of a year and means. The alive cost of the works is of about 40 million euros.

ABB Marine Solutions
Consorzio ZAI



Search for hotel
Destination
Check-in date
Check-out date








Index Home Page News

- Piazza Matteotti 1/3 - 16123 Genoa - ITALY
phone: +39.010.2462122, fax: +39.010.2516768, e-mail